CE-UWL Installation Guide for Buyers & Contractors

The CE-UWL needs a 1030 × 895 mm floor area with clearance, 380V/50Hz/3-phase power at 27.4 kW, a ¾" water inlet and 1½" drain, and a φ175 mm exhaust path. Confirm these before the machine ships to avoid installation delays.

POTWASHER CE-UWL installed with an overhead exhaust duct, inspected at the factory before shipment

Site requirements summary

Plan for floor space and clearance, ceiling height for steam, an exhaust path, three-phase power, a water inlet and outlet, and floor drainage near the machine.

Power

  • Standard: 380V / 50Hz / 3PH; option: 220V / 50Hz / 1PH
  • Total connected load: 27.4 kW
  • Supply cable: 10 mm² with an appropriately-rated breaker

Water

  • Inlet: ¾" at 0.2–0.5 MPa
  • Outlet/drain: 1½" with a trap nearby
  • Recommended hardness: < 5 °dH, otherwise fit a softener

Exhaust & floor

  • Exhaust: φ175 mm pipe to an overhead hood
  • Floor: level concrete with a drain nearby

Footprint & clearance

External dimensions are 1030 × 895 × 1825 mm. Allow front clearance for the fold-down door and loading, plus rear access for plumbing and exhaust. Verify the crated machine can route through doorways and corridors to the install point.

Commissioning

  1. Factory pre-test before shipment.
  2. On-site setup and connection by local trades.
  3. Calibration and dry-run, guided remotely over WhatsApp video.
  4. Operator training.

Installation checklist (PDF)